8.3 PT31 Torch
Test Procedure for PT31XLPC torch
Equipment Required:
A. Supply of 100 PSI Air or Nitrogen gas with regulator.
B. Test xture P/N PG-071-16.
C. Reference documents:
Description PT-31
Assembly drawings 20072
Instruction Manual F-14-246-J
Visual Inspection:
Determine that all components are properly located and securely
mounted. Check copper tube for proper angle and tightness; watch
for interference with other connections and shorts. Check power
cable connector for damaged threads.
Test Set-Up:
A. Verify that the power switch on bench is in the OFF position.
B. Verify that the bench Nitrogen switch is in the OFF position.
C. Verify that the bench Leak I switch is in the OFF position.
D. Connect the Nitrogen gas hose from xture to supply line.
E. Attach the PT-31 torch to test xture mark Torch Connection.
Test:
A. Turn the power switch on bench to the ON position.
B. Turn Nitrogen switch to bench test xture ON.
C. Turn the Leak I switch on bench test xture ON.
D. Verify that the valve on ow meter is to the ON position.
E. Adjust the pressure regulator is to read 45 PSI on pressure
gauge.
F. Observe the ball in the ow meter. If any reading of CFH the
torch body is bad.
G. Turn the Leak I switch on bench test xture OFF.
Final Check:
If the visual checks of the torch and test items E and F are
accomplished satisfactorily, then remove torch from test xture and
identify as tested and passed.